Do and Don't: Contractor Bids, Draws and Lien Waivers
Money moves between the investor and the contractor dozens of times on a renovation, and each payment is a chance to protect or weaken the project. A clear bid process and a disciplined payment schedule matter more than finding the lowest number. The guidance below is grouped by stage, and each point carries its reason.
Collecting and comparing bids
- Do give every bidder the same written scope. Bids built on different assumptions cannot be compared, and the cheapest one is often cheapest because it leaves items out.
- Don’t accept a single lump sum with no breakdown. Line-item pricing shows where a bid is thin and lets you remove or add work later without renegotiating everything.
- Do ask who pulls permits and who is licensed for each trade. Texas has no statewide general-contractor licence, but electrical and air-conditioning work requires TDLR-licensed contractors, plumbing requires a Texas state plumbing licence, and your city may require contractor registration.
- Do ask for proof of liability insurance and, where the contractor has employees, workers’ compensation or an explanation of how injuries are covered. An uninsured injury on your property becomes your problem.
- Don’t ignore start dates. A cheaper bid that cannot begin for six weeks may cost more in holding than it saves.
Paying as work is finished
| Stage | Do | Don’t |
|---|---|---|
| Deposit | Keep it modest and tied to materials ordered for your job. | Pay a large share before anything is on site. |
| Progress draws | Tie each draw to a defined, inspectable milestone (rough-in passed, drywall hung, cabinets set). | Pay by calendar date or because the crew asks. |
| Change orders | Price and sign each change before the work is done. | Approve extras verbally and argue about the bill later. |
| Final payment | Hold it until the punch list is complete and permits are finaled. | Release it when the house “looks done.” |
Lien waivers and records
In Texas, unpaid subcontractors and suppliers can have lien rights against the property even if you paid the general contractor. That is why investors collect lien waivers with each draw, from the contractor and, for larger jobs, from major subcontractors and suppliers. Texas uses statutory waiver and release forms for this purpose; ask a Texas construction or real estate attorney which form applies to each payment and how conditional and unconditional waivers differ. A title company preparing your resale may ask about recent work, so a clean folder of waivers and paid invoices can save time at closing.
- ☐ Signed written contract that references the scope of work
- ☐ Certificate of insurance on file
- ☐ Draw schedule agreed in writing
- ☐ Lien waiver received for every payment
- ☐ Permit numbers and final inspection results recorded
- ☐ Warranty terms from each trade saved for the buyer
This page describes common practice in general terms. Lien law has strict notice and timing rules; for your project, rely on an attorney rather than a summary.
Sources and further reading
- Texas Department of Licensing and Regulation (TDLR) — licenses electricians and air conditioning and refrigeration contractors, with an online licence search.
- International Code Council — International Residential Code (IRC), adopted with local amendments by many cities.
- Federal Trade Commission — consumer guidance on real estate and home-improvement scams.